Off-Plan Property Funds and Escrow Rules in Saudi Arabia

This reference guide details the legal safeguards, escrow account structures, delay remedies and registration authorities governing off-plan residential and commercial purchases in Saudi Arabia.

30 August 2026
Riyadh, Saudi Arabia
A general view of Riyadh. File photograph, not of the property described. B.alotaby · CC BY-SA 4.0
The short answer
Off-plan regulatory authority
Real Estate General Authority (REGA)
Off-plan licensing regime
Wafi Program
National land registry
Real Estate Registry (RER)
Property transfer tax
5% Real Estate Transaction Tax (RETT) as of 2026
Rules checked August 2026. Rates and procedures change; each source is listed below.

Legal Framework and Escrow Requirements

Buying an off-plan property in Saudi Arabia requires navigating a statutory framework managed by the Real Estate General Authority (REGA). Off-plan developments operate under the Law of Off-Plan Sale and Lease of Real Estate Projects (commonly referenced under the Wafi regulatory framework). Under this regime, developers are legally prohibited from selling units prior to full construction without securing a project-specific licence from REGA.

To safeguard buyer funds, Saudi law mandates the opening of a dedicated project escrow account with an approved local bank for every licensed off-plan scheme. Developers cannot receive direct payments into corporate operating accounts. All buyer deposits, milestone payments, and bank financing disbursements must be paid directly into the designated project escrow account. The account is supervised by REGA alongside an independent financial auditor and a certified engineering consultant. Funds are released to the developer strictly in tranches linked to certified construction milestones verified on-site by the project consultant.

Payment Schedules and Milestone Structures

Off-plan payment structures in Riyadh are tied to physical construction progress rather than fixed calendar dates. While commercial terms vary, a standard payment model follows a defined progression:

  • Initial Reservation Deposit: Paid upon signing the reservation agreement to secure the plot or unit.
  • Contract Signing (Foundation Stage): Paid upon execution of the off-plan sale contract following REGA clearance and completion of excavation and foundational works.
  • Structural Milestones: Paid in tranches as key construction stages are completed, such as sub-structure, concrete framing, cladding, and mechanical, electrical and plumbing (MEP) rough-ins.
  • Completion and Handover: The remaining balance is released upon physical completion, verification by REGA inspectors, and formal registration.

Under REGA rules, developers must keep a mandatory financial buffer within the escrow account to cover snagging, structural guarantees, and defect liabilities post-completion.

Remedies for Construction Delays and Developer Failure

If a developer fails to hand over a project within the contractually agreed timeframe, REGA and the Wafi framework set out formal procedures. Off-plan sales contracts must include an expected completion date and specific penalty clauses for unjustified delays. Where delays occur without an approved extension, buyers are entitled to financial compensation outlined in the contract, typically calculated as a percentage of the purchase price or rental value per month of delay.

In cases of severe insolvency, abandonment, or structural failure by the developer, REGA holds statutory powers to intervene. Escrow funds remain protected from general creditors of the developer. If a project is cancelled or deemed unviable by the regulator, the remaining capital held in the escrow account is preserved for refunding buyers. REGA may also force a transfer of the project and land title to another developer to complete construction.

Property Verification and Registration Systems

Before executing a contract or transferring funds, buyers must confirm that both the developer and the specific project hold valid licences. REGA maintains an electronic register of licensed real estate developers and approved off-plan projects.

Final title registration and ownership records are processed through the National Real Estate Registration Services Company (Real Estate Registry or RER), operating under REGA oversight. The RER creates a centralised digital database linking ownership rights directly to spatial and parcel data. Title deeds are issued electronically, replacing the historical reliance on notary public deeds alone for designated zones. Buyers can verify project licences, developer status, and land ownership records using REGA’s online platforms and the official RER portal prior to committing capital.

Real Estate Transaction Tax (RETT) applies to real estate transfers in Saudi Arabia at a flat rate of 5%. For off-plan purchases, RETT is generally assessed and due upon the execution and registration of the sale contract or transfer according to Zakat, Tax and Customs Authority (ZATCA) regulations.

Common questions

Is an escrow account mandatory for off-plan property sales in Saudi Arabia?
Yes, Saudi law mandates that every licensed off-plan real estate project must have a dedicated escrow account established at a licensed bank. All buyer payments are deposited into this account and released only when certified construction milestones are met.
Which authority regulates off-plan real estate sales in Riyadh?
Off-plan developments in Riyadh and across Saudi Arabia are regulated by the Real Estate General Authority (REGA) under the Wafi program framework.
Are buyer deposits recoverable if an off-plan developer fails?
Yes, because funds are kept in a project-specific escrow account monitored by REGA, unspent money cannot be accessed by the developer's general creditors. If a project is officially cancelled, escrow funds are used to refund purchasers.
How can a buyer check if an off-plan project is legally licensed?
Buyers can verify a project's approval status and developer credentials online via REGA's official portal and the Real Estate Registry (RER) system.
What happens if a developer delivers an off-plan property late?
Standard REGA-compliant off-plan contracts contain delay compensation provisions. If handover exceeds the agreed date without an approved extension, the developer must pay compensation specified in the contract.
What property tax applies when buying an off-plan home in Saudi Arabia?
Off-plan property transfers are subject to the Real Estate Transaction Tax (RETT), which is set at a rate of 5%.
Sources
  1. trowers.com. trowers.com
  2. kfirm.co. kfirm.co
  3. rega.gov.sa. rega.gov.sa
  4. tamimi.com. tamimi.com
  5. bankalbilad.com.sa. bankalbilad.com.sa
  6. lexismiddleeast.com. lexismiddleeast.com
  7. rega.gov.sa. rega.gov.sa
  8. rega.gov.sa. rega.gov.sa

Compiled by the Propstock research desk from the sources above.